Refit · interior upgrade
New build · full interior outfitting
46 m motor yacht — complete interior outfitting
Gulf shipyard · 2025 · 14 months
Scope
- Joinery for six guest and four crew cabins
- Saloon, sky lounge and dining furniture, fixed and loose
- Vanities, stone tops and wet-area fittings
- Lighting, hardware and leather upholstery
Challenge
The block sequence moved twice while the interior specification was still being finalised.
What we did
A rolling bill of materials against the GA, production released in three tranches, all categories consolidated into four shipments timed to block closure.
Outcome
Delivered inside the revised programme with no class comments and no re-work on fit.
More
Other projects
Loose furniture supply package